Skip to content

Efficient Asphalt Replacement at Home Depot Facility

In response to the need for rapid pavement replacement at a Home Depot facility, Gallagher Asphalt Corporation executed and expedited an asphalt project. The task involved the removal of existing 5” Hot Mix Asphalt (HMA) and 7” of aggregate, replaced by a robust 12” asphalt section composed of N90 binder (10”) and N80 surface (2”). The project's distinct challenge was to complete the entire process within a strict 37-hour timeline, emphasizing the priority of opening the dock doors for incoming shipments by noon on Sunday.

Download this Resource